Brave Tern and Bold Tern successfully completed transportation and installation of 47 wind turbines at Formosa 2 offshore wind farm in Taiwan.
The new windfarm will provide Taiwan with clean energy and assist its transition towards using more renewable energy. With 47 SG 8.0-167 DD turbines, it will generate 376MW, and generate enough electricity to power the equivalent of approximately 380,000 households.
Jack-up vessel Brave Tern began the installation process in June 2022 and was replaced by the newly upgraded Bold Tern in August. Both vessels then teamed up to finish the project, the installation was successfully completed on 31st January 2023.