Fred. Olsen Windcarrier (FOWIC) has won a contract with jack-up installation vessel the Blue Tern for supporting the jacket installation campaign on the Neart na Goithe (NnG) offshore wind farm. The contract is included in FOWIC’s disclosed total backlog with a value of approximately EUR 355 million.
Blue Tern will support the jacket installation campaign by doing drilling and possibly piling works. In early May of 2022, Saipem started mobilisation work on the Blue Tern in Esbjerg. After this, she will transit to Blyth to start the work on NnG. Back in late February, Blue Tern left Fayard in Demnark where she underwent upgrade work and then went straight on to the Kaskasi project off the coast of the German Island Helgoland.